Regional Project Profile

Wissahickon Valley Watershed Association

Category: Implemented Retrofit  
Type of BMP:
Porous paving, dry well, rain barrels, constructed wetland

| Description | Location | Partners | Cost | Contact |
 

 Description

To provide enhanced stormwater management on its properties, WVWA implemented the following BMPs: 1) Porous paving; 2) Dry well; 3) Rain barrels; 4) Constructed wetland.  Photos of the BMPs taken by Bob Adams follow.

1) Porous Paving
Plastic pervious paving grids were installed on the grounds of WVWA’s headquarters in 2002 and concrete paving grids were installed in 1991. The earth was leveled at approximately one foot below existing grade and filled with fist-sized stone to create stormwater storage capacity. These grids allow for water and pollutants to penetrate the soil underneath the grid, while still providing structural support for vehicles. Because grass grows within the grid squares, the area is natural looking, retains much less heat than traditional asphalt and reduces the velocity with which stormwater flows off the surface of the ground. Since stormwater has time to percolate into the ground and filter, pollutants associated with parking lots are not washed right off of pavement into waterways. Mowing is the only maintenance work required.  Click here for a picture of WVWA's concrete pervious pavement.  Click here for a picture of on site plastic pervious pavement.

2) Dry Well
A dry well was built to effectively retain excess drainpipe water during periods of excessive rainfall. To build a dry well the WVWA dug a hole, used grid left over from the pervious parking grid to create a frame, filled the hole with riverstone and placed a 4” PVC pipe on end.  Click here for a photo of WVWA's dry well.

3) Rain Barrels
Rainwater falling on Four Mills Barn is collected from drain pipes and is stored in twin rain barrels. This water is recycled by serving as a reserve for watering plants on site. WVWA disconnects the drain pipes, drains, and seals the rain barrels during the winter to prevent damage from freezing.  Click here for a photo of one of WVWA's rainbarrels.

4) Constructed Wetland
The Sandy Run stormwater wetland’s first phase was started in spring 2006. Trees were planted upstream from the wetland in order to cool the water temperatures in the creek, increasing oxygenation. Within the wetland itself, clay silt, which had been deposited over the years, was removed with the help of heavy machinery. The wetland’s bottom was somewhat staggered in height to create different zones for various aquatic plants. Native wetland vegetation was restored within the basin and a vegetative riparian buffer was created. Since geese are often intrusive and destructive to wetland projects, design strategies to keep them away included tall wetland plants, a vegetative buffer, and geese barriers. Geese barriers, made of stakes and string forming a grid system, also were installed to prevent both geese and deer from consuming juvenile plants.

The wetland’s maintenance plans over the first five years include the inspection for and removal of invasive species. Interpretive signs are planned to be placed on site as well. Other plans for the site include a 2007 extension of the Montgomery County Cross Country Trail to be built alongside the wetland, and large-scale expansion of the wetland’s total area, which is expected to double in 2008. For a plant list for the constructed wetland, click here
 

WVWA Headquarters: Four Mills Barn
Photo Credit: Bob Adams

Constructed Wetland at Sandy Run
Photo Credit: Bob Adams

 Location

County:         Montgomery County
Watershed:   Wissahickon Creek

The Wissahickon Valley Watershed Association (WVWA) is located at 12 Morris Drive in the borough of Ambler, Pennsylvania. Since its inception more than 50 years ago, the WVWA has promoted intelligent land use practices, preservation of environmentally sensitive and historic sites, and has worked on public education initiatives. The WVWA now maintains more than a thousand acres of preserved land in the Wissahickon watershed. The WVWA has installed various Best Management Practices (BMPs) on their lands. At Four Mills Barn, the headquarters of the WVWA, several BMPs have been erected around the barn and serve as a model to local commercial and residential proprietors about the ease and utility of their presence. The WVWA also implemented a wetland restoration project along Sandy Run. The Sandy Run stormwater wetland is located in Whitemarsh Township one-tenth of a mile from the R-5 Fort Washington railroad station at a busy intersection at Bethlehem Pike and Lafayette Road. The wetland is a 3-acre restoration project located less than 2 miles from WVWA headquarters and is protected land under WVWA’s stewardship. The wetland area along Sandy Run was a strategic area to retrofit because of its high visibility to the public, the high magnitude of stormwater runoff in its vicinity, and the tributary is a contribution of non-point pollution flowing into the Wissahickon Creek.
 

 Partners
WVWA, PECO Energy, the EPA, and The Environmental Leadership Program
 
 Cost
Rain barrels around $160 each. Dry well about $40. Porous pavement from $600-$700 per parking space.

The Sandy Run stormwater wetland restoration about $42,000. EPA grant of $40,000.
 

 Contact

Bob Adams
Wissahickon Valley Watershed Association
12 Morris Drive, Ambler, PA 19002
Phone: (215) 426-8866
Bob@wvwa.org

 
 
| Contact webmaster |

Copyright © 2006-2008 [Center for Sustainable Communities]. All rights reserved.